Project Name Building 1100 Learning Resource Center Renovation
CFIS 40.71.111
District YUBA DISTRICT
College YUBA COLLEGE
City Marysville
County Yuba
Senate District 4
Assembly District 3
Project Description and Status
Project Type Modernize Instruction
Date Funded 2/20/2009
Project Description This proposed project modernizes the existing Learning Resource Center (LRC) at Yuba College to provide consolidated and expanded space through more efficient configurations. The proposed 34,859 asf reconstruction project will result in 20,768 asf library space, 10,259 asf AV/TV space, 3,019 asf office space and 813 asf other support space such as meeting rooms and data/processing rooms.
Project Status Construction Complete
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 8/1/2009 7/23/2009
Preliminary Planning Approved, Design Begins 1/1/2010 5/17/2010
Design Approved, Authorized to go to Bid 7/1/2011 5/24/2011
Construction Begins 5/1/2012 5/14/2012
Facility Enters Into Use 1/18/2014 12/1/2013
Project Closeout
Project Budget Summary
State Financing $8,320,000
Local/Non-State Financing $10,738,661
Total Financing $19,058,661
State Contact Lan Yuan
lyuan@cccco.edu
District Contact Kuldeep Kaur
5307416723
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $371,000 $371,000 $742,000
Working Drawings $506,000 $478,533 $984,533
Construction $6,558,000 $9,019,373 $15,577,373
Equipment $885,000 $869,755 $1,754,755
Total Project Financing $8,320,000 $10,738,661 $19,058,661
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $742,000 $0 $742,000
Working Drawings $1,012,000 $54,934 $957,066
Construction $18,652,000 $3,074,627 $15,577,373
Contract $17,692,000 $3,074,627 $14,617,373
Allowances $960,000 $0 $960,000
Equipment $1,770,000 $30,490 $1,739,510
Total Project Financing $22,176,000 $3,160,051 $19,015,949