California Community Colleges Proposition 1D Project Details
Project Name Science and Math Building Renovation
CFIS 40.69.110
District WEST VALLEY COMMUNITY COLLEGE DISTRICT
College WEST VALLEY COLLEGE
City Saratoga
County Santa Clara
Senate District 15
Assembly District 24
Project Description and Status
Project Type Modernize Instruction
Date Funded 6/30/2006
Project Description The project reconstructs the 37,509 square foot Science Mathematics Building built in 1969. The project will renovate 9,510 square feet (sf) of lecture, 23,182 sf of laboratories, 3,834 sf of office and 983 sf of other space. Presently, the building provides instructional space for physical science, life science and art programs and no changes are expected during the project in the building’s instructional programming.
Project Status Construction Complete
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 6/1/2007 11/14/2006
Preliminary Planning Approved, Design Begins 12/1/2007 11/9/2007
Design Approved, Authorized to go to Bid 6/1/2009 5/12/2009
Construction Begins 8/1/2009 9/10/2009
Facility Enters Into Use 11/1/2011
Project Closeout
Project Budget Summary
State Financing $15,849,000
Local/Non-State Financing $3,381,899
Total Financing $19,230,899
State Contact Harold Flood
hflood@cccco.edu
District Contact Javier Castruita
4087412042
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $717,000 $55,096 $772,096
Working Drawings $960,000 $351,757 $1,311,757
Construction $14,172,000 $2,375,528 $16,547,528
Equipment $0 $599,518 $599,518
Total Project Financing $15,849,000 $3,381,899 $19,230,899
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $717,000 $55,096 $772,096
Working Drawings $960,000 $351,757 $1,311,757
Construction $18,475,000 $2,375,528 $20,850,528
Contract $17,427,000 $1,743,129 $19,170,129
Allowances $1,048,000 $632,399 $1,680,399
Equipment $0 $599,518 $599,518
Total Project Financing $20,152,000 $3,381,899 $23,533,899