California Community Colleges Proposition 1D Project Details
Project Name Science and Math Replacement
CFIS 40.69.106
District WEST VALLEY COMMUNITY COLLEGE DISTRICT
College WEST VALLEY COLLEGE
City Saratoga
County Santa Clara
Senate District 15
Assembly District 24
Project Description and Status
Project Type Expand Instruction
Date Funded 7/31/2004
Project Description The project expands chemistry laboratory space on the West Valley College Campus by 6,054 square feet.
Project Status Construction Complete
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 2/1/2005 8/2/2004
Preliminary Planning Approved, Design Begins 2/1/2006 1/17/2006
Design Approved, Authorized to go to Bid 11/1/2007 11/30/2007
Construction Begins 12/14/2007 4/7/2008
Facility Enters Into Use 12/31/2008 7/12/2010
Project Closeout
Project Budget Summary
State Financing $5,629,000
Local/Non-State Financing $815,759
Total Financing $6,444,759
State Contact Harold Flood
hflood@cccco.edu
District Contact Javier Castruita
4087412042
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $267,000 $0 $267,000
Working Drawings $119,000 $0 $119,000
Construction $4,848,000 $815,759 $5,663,759
Equipment $395,000 $0 $395,000
Total Project Financing $5,629,000 $815,759 $6,444,759
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $267,000 $0 $267,000
Working Drawings $119,000 $0 $119,000
Construction $3,287,000 $2,376,759 $5,663,759
Contract $3,048,000 $2,041,075 $5,089,075
Allowances $239,000 $335,684 $574,684
Equipment $0 $395,000 $395,000
Total Project Financing $3,673,000 $2,771,759 $6,444,759