Project Name TIL Center
CFIS 40.68.105
District WEST KERN COMMUNITY COLLEGE DISTRICT
College TAFT COLLEGE
City Taft
County Kern
Senate District 18
Assembly District 32
Project Description and Status
Project Type Support Instruction
Date Funded 8/24/2007
Project Description The project constructs a new 14,104 square foot Transition to Independent Living (TIL) Center with 3,090 square feet (sf) of office, 10,216 sf of demonstration, 405 sf of meeting rooms, and 393 sf of other space.
Project Status Construction Complete
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 8/28/2007 8/28/2007
Preliminary Planning Approved, Design Begins 6/17/2008 6/17/2008
Design Approved, Authorized to go to Bid 5/17/2010 5/17/2010
Construction Begins 5/24/2011 5/24/2011
Facility Enters Into Use 4/20/2013 9/11/2013
Project Closeout
Project Budget Summary
State Financing $10,541,000
Local/Non-State Financing $4,531,000
Total Financing $15,072,000
State Contact Cheryl Larry
clarry@cccco.edu
District Contact Kevin Cobb AIA/ARA
6613271690
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $115,000 $296,000 $411,000
Working Drawings $561,000 $56,000 $617,000
Construction $9,451,000 $4,179,000 $13,630,000
Equipment $414,000 $0 $414,000
Total Project Financing $10,541,000 $4,531,000 $15,072,000
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $411,000 $0 $411,000
Working Drawings $617,000 $0 $617,000
Construction $11,735,000 $1,895,000 $13,630,000
Contract $11,092,000 $1,895,000 $12,987,000
Allowances $643,000 $0 $643,000
Equipment $414,000 $0 $414,000
Total Project Financing $13,177,000 $1,895,000 $15,072,000