California Community Colleges Proposition 1D Project Details
Project Name Wellness Center
CFIS 40.67.104
District WEST HILLS COMMUNITY COLLEGE DISTRICT
College WEST HILLS COLLEGE COALINGA
City Coalinga
County Kern
Senate District 16
Assembly District 30
Project Description and Status
Project Type Support Instruction
Date Funded 6/30/2006
Project Description The project renovates 18,211 square feet (sf) in the existing gym complex, constructs an adjacent 7,624 square foot facility for adaptive physical education and rehabilitation programs, and provides for the demolition of two portable facilities.
Project Status State Accounts Closed
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 7/1/2006 11/20/2006
Preliminary Planning Approved, Design Begins 10/1/2006 8/10/2007
Design Approved, Authorized to go to Bid 1/1/2007 5/19/2008
Construction Begins 9/1/2007 6/25/2008
Facility Enters Into Use 11/1/2008 2/5/2012
Project Closeout 3/1/2013
Project Budget Summary
State Financing $7,561,000
Local/Non-State Financing $1,891,000
Total Financing $9,452,000
State Contact Hoang Nguyen
hnguyen@cccco.edu
District Contact Kevin Cobb
6613271690
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $119,000 $212,000 $331,000
Working Drawings $190,000 $251,000 $441,000
Construction $7,147,000 $1,428,000 $8,575,000
Equipment $105,000 $0 $105,000
Total Project Financing $7,561,000 $1,891,000 $9,452,000
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $331,000 $0 $331,000
Working Drawings $441,000 $0 $441,000
Construction $8,814,000 $239,000 $8,575,000
Contract $8,317,000 $239,000 $8,078,000
Allowances $497,000 $0 $497,000
Equipment $105,000 $0 $105,000
Total Project Financing $9,691,000 $239,000 $9,452,000