California Community Colleges Proposition 1D Project Details
Project Name Music Buildings 800/850 Remodel
CFIS 40.63.108
District SOUTHWESTERN COMMUNITY COLLEGE DISTRICT
College SOUTHWESTERN COLLEGE
City Chula Vista
County San Diego
Senate District 40
Assembly District 78
Project Description and Status
Project Type Modernize Instruction
Date Funded 6/30/2006
Project Description The project renovates 13,444 square feet (sf) in buildings 800 and 850. These buildings were built in 1965 and 1975 respectively and are utilized primarily by the Music programs. The renovated space will consist of 2,131 sf of lecture, 9,756 sf of laboratory, 797 sf of office, 554 sf of technology space and 206 sf of other space.
Project Status State Accounts Closed
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 9/1/2006 11/17/2006
Preliminary Planning Approved, Design Begins 12/1/2006 1/15/2007
Design Approved, Authorized to go to Bid 9/1/2007 5/24/2007
Construction Begins 11/1/2007 6/27/2007
Facility Enters Into Use 12/1/2008 11/21/2008
Project Closeout 3/24/2010
Project Budget Summary
State Financing $3,005,000
Local/Non-State Financing $3,537,000
Total Financing $6,542,000
State Contact Carlos Montoya
cmontoya@cccco.edu
District Contact John R. Brown P.E.
6194826320
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $72,000 $176,000 $248,000
Working Drawings $35,000 $210,000 $245,000
Construction $2,400,000 $3,151,000 $5,551,000
Equipment $498,000 $0 $498,000
Total Project Financing $3,005,000 $3,537,000 $6,542,000
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $233,000 $15,000 $248,000
Working Drawings $269,000 $24,000 $245,000
Construction $4,892,000 $659,000 $5,551,000
Contract $4,544,000 $650,000 $5,194,000
Allowances $348,000 $9,000 $357,000
Equipment $498,000 $0 $498,000
Total Project Financing $5,892,000 $650,000 $6,542,000