California Community Colleges Proposition 1D Project Details
Project Name Public Safety Training Center Advanced Laboratory and Office Complex
CFIS 40.61.401
District SONOMA COUNTY JUNIOR COLLEGE DISTRICT
College PUBLIC SAFETY TRAINING CENTER
City Windsor
County Sonoma
Senate District 2
Assembly District 1
Project Description and Status
Project Type Expand Instruction
Date Funded 8/24/2007
Project Description The project constructs an 11,953 square foot advanced laboratory building. Space types in the building include 935 square feet (sf) of lecture, 8,751 sf of laboratory, 1,114 sf of office, and 1,153 sf of other space.
Project Status State Accounts Closed
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 7/3/2007 8/29/2007
Preliminary Planning Approved, Design Begins 7/1/2008 5/9/2008
Design Approved, Authorized to go to Bid 7/1/2009
Construction Begins 9/1/2009
Facility Enters Into Use 10/1/2010
Project Closeout 5/1/2011
Project Budget Summary
State Financing $298,000
Local/Non-State Financing $2,857,378
Total Financing $3,155,378
State Contact Jim Rogaski
jrogaski@cccco.edu
District Contact Tony Ichsan
7075274432
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $143,000 $142,000 $285,000
Working Drawings $155,000 $155,000 $310,000
Construction $0 $2,560,378 $2,560,378
Equipment $0 $0 $0
Total Project Financing $298,000 $2,857,378 $3,155,378
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $285,000 $0 $285,000
Working Drawings $310,000 $0 $310,000
Construction $7,779,000 $244,378 $8,023,378
Contract $7,359,000 $244,378 $7,603,378
Allowances $420,000 $0 $420,000
Equipment $285,000 $0 $285,000
Total Project Financing $8,659,000 $244,378 $8,903,378