California Community Colleges Proposition 1D Project Details
Project Name Child Development Center
CFIS 40.58.108
District SIERRA JT. COMMUNITY COLLEGE DISTRICT
College SIERRA COLLEGE
City Rocklin
County Placer
Senate District 4
Assembly District 4
Project Description and Status
Project Type Support Instruction
Date Funded 8/24/2007
Project Description The project constructs a 14,144 square foot child development facility with 1,206 square feet (sf) of laboratory, 1,761 sf of office, 265 sf of library, and 10,912 sf of other space of which 9,983 sf is child development demonstration space.
Project Status In Final Design
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 1/5/2008 8/28/2007
Preliminary Planning Approved, Design Begins 5/10/2008 5/9/2008
Design Approved, Authorized to go to Bid 5/15/2016
Construction Begins 7/15/2016
Facility Enters Into Use 10/15/2017
Project Closeout
Project Budget Summary
State Financing $560,000
Local/Non-State Financing $498,000
Total Financing $1,058,000
State Contact Carlos Montoya
cmontoya@cccco.edu
District Contact Laura Doty
9166607650
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $349,000 $0 $349,000
Working Drawings $211,000 $0 $211,000
Construction $0 $498,000 $498,000
Equipment $0 $0 $0
Total Project Financing $560,000 $498,000 $1,058,000
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $349,000 $0 $349,000
Working Drawings $351,000 $0 $351,000
Construction $7,416,000 $2,568,000 $9,984,000
Contract $6,921,000 $2,430,000 $9,351,000
Allowances $495,000 $138,000 $633,000
Equipment $405,000 $75,000 $480,000
Total Project Financing $8,521,000 $2,643,000 $11,164,000