California Community Colleges Proposition 1D Project Details
Project Name P.E.& Disabled Prog. Facility
CFIS 40.56.111
District SEQUOIAS COMMUNITY COLLEGE DISTRICT
College COLLEGE OF THE SEQUOIAS
City Visalia
County Tulare
Senate District 18
Assembly District 34
Project Description and Status
Project Type Support Instruction
Date Funded 8/2/2003
Project Description The project constructs a new 20,535 square foot gymnasium and a new 1,794 square foot disable program center and reconstructs 6,360 square feet in the existing gymnasium.
Project Status State Accounts Closed
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 8/8/2003
Preliminary Planning Approved, Design Begins 2/6/2004
Design Approved, Authorized to go to Bid 4/1/2009 9/25/2008
Construction Begins 6/1/2009 12/8/2008
Facility Enters Into Use 12/1/2010 12/1/2010
Project Closeout 2/27/2014
Project Budget Summary
State Financing $12,207,000
Local/Non-State Financing $43,000
Total Financing $12,250,000
State Contact Lan Yuan
lyuan@cccco.edu
District Contact Eric Mittlestead
5597303908
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $211,000 $3,000 $214,000
Working Drawings $294,000 $3,000 $297,000
Construction $11,368,000 $36,000 $11,404,000
Equipment $334,000 $1,000 $335,000
Total Project Financing $12,207,000 $43,000 $12,250,000
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $214,000 $0 $214,000
Working Drawings $297,000 $0 $297,000
Construction $6,406,000 $4,998,000 $11,404,000
Contract $6,013,000 $4,613,000 $10,626,000
Allowances $393,000 $385,000 $778,000
Equipment $252,000 $83,000 $335,000
Total Project Financing $7,169,000 $5,081,000 $12,250,000