California Community Colleges Proposition 1D Project Details
Project Name Student Services and Administration Bldg.
CFIS 40.55.110
District SANTA MONICA COMMUNITY COLLEGE DISTRICT
College SANTA MONICA COLLEGE
City Santa Monica
County Los Angeles
Senate District 23
Assembly District 41
Project Description and Status
Project Type Expand Institution
Date Funded 8/24/2007
Project Description The project constructs a 53,505 square foot student services/administration building. Space types in the building include 2,442 square feet (asf) of lecture , 1,940 sf of laboratory space, 39,589 sf of office space and administrative support space, 1,354 sf of library space and 8,180 sf of other space.
Project Status State Accounts Closed
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 7/1/2007 8/29/2007
Preliminary Planning Approved, Design Begins 4/1/2008 5/9/2008
Design Approved, Authorized to go to Bid 12/20/2012 12/1/2012
Construction Begins 3/5/2013
Facility Enters Into Use 10/31/2015
Project Closeout 2/7/2014
Project Budget Summary
State Financing $1,321,000
Local/Non-State Financing $89,612,252
Total Financing $90,933,252
State Contact Jim Rogaski
jrogaski@cccco.edu
District Contact Gregory Brown
3104344203
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $684,000 $3,452,729 $4,136,729
Working Drawings $637,000 $5,784,643 $6,421,643
Construction $0 $78,385,814 $78,385,814
Equipment $0 $1,989,066 $1,989,066
Total Project Financing $1,321,000 $89,612,252 $90,933,252
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $1,982,000 $2,154,729 $4,136,729
Working Drawings $1,984,000 $4,437,643 $6,421,643
Construction $48,860,000 $45,007,814 $93,867,814
Contract $46,648,000 $43,260,024 $89,908,024
Allowances $2,212,000 $1,747,790 $3,959,790
Equipment $906,000 $1,536,066 $2,442,066
Total Project Financing $53,732,000 $53,136,252 $106,868,252