California Community Colleges Proposition 1D Project Details
Project Name Library Addition
CFIS 40.54.116
District SANTA CLARITA COMMUNITY COLLEGE DISTRICT
College COLLEGE OF THE CANYONS
City Santa Clarita
County Los Angeles
Senate District 19
Assembly District 38
Project Description and Status
Project Type Expand Instruction
Date Funded 8/24/2007
Project Description The project constructs a 37,345 square foot addition to the existing library building. Space types in the building will include 9,910 square feet (sf) of laboratory, 26,505 sf of library space, and 930 sf of other space.
Project Status Construction Complete
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 11/1/2007 8/29/2007
Preliminary Planning Approved, Design Begins 7/1/2008 6/17/2008
Design Approved, Authorized to go to Bid 3/1/2010 4/21/2010
Construction Begins 5/1/2010 10/26/2010
Facility Enters Into Use 8/1/2012 12/1/2012
Project Closeout
Project Budget Summary
State Financing $9,414,000
Local/Non-State Financing $6,525,000
Total Financing $15,939,000
State Contact Eric Thorson
ethorson@cccco.edu
District Contact Jim Schrage
6613623222
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $207,000 $553,000 $760,000
Working Drawings $247,000 $705,000 $952,000
Construction $6,803,000 $4,526,000 $11,329,000
Equipment $2,157,000 $741,000 $2,898,000
Total Project Financing $9,414,000 $6,525,000 $15,939,000
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $760,000 $0 $760,000
Working Drawings $952,000 $0 $952,000
Construction $20,171,000 $8,842,000 $11,329,000
Contract $19,178,000 $8,470,000 $10,708,000
Allowances $993,000 $372,000 $621,000
Equipment $2,841,000 $57,000 $2,898,000
Total Project Financing $24,724,000 $8,785,000 $15,939,000