California Community Colleges Proposition 1D Project Details
Project Name University Center
CFIS 40.54.115
District SANTA CLARITA COMMUNITY COLLEGE DISTRICT
College COLLEGE OF THE CANYONS
City Santa Clarita
County Los Angeles
Senate District 19
Assembly District 38
Project Description and Status
Project Type Expand Instruction
Date Funded 6/30/2006
Project Description The project constructs a 39,650 square foot university center instructional building. Space types in the building will include 2,650 square feet (sf) of lecture space, 23,900 sf of laboratory space, 6,340 sf of office space, 1,000 sf of library space, 720 sf of technology space, and 5,040 sf of other space.
Project Status State Accounts Closed
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 7/1/2006 11/16/2006
Preliminary Planning Approved, Design Begins 7/1/2007 7/13/2007
Design Approved, Authorized to go to Bid 12/1/2007 8/10/2007
Construction Begins 2/1/2008 12/7/2007
Facility Enters Into Use 7/1/2009 4/15/2010
Project Closeout 5/27/2010
Project Budget Summary
State Financing $20,974,000
Local/Non-State Financing $15,366,000
Total Financing $36,340,000
State Contact Eric Thorson
ethorson@cccco.edu
District Contact Jim Schrage
6613623222
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $185,000 $657,000 $842,000
Working Drawings $235,000 $667,000 $902,000
Construction $17,849,000 $12,883,000 $30,732,000
Equipment $2,705,000 $1,159,000 $3,864,000
Total Project Financing $20,974,000 $15,366,000 $36,340,000
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $842,000 $0 $842,000
Working Drawings $902,000 $0 $902,000
Construction $22,589,000 $8,142,800 $30,731,800
Contract $21,465,000 $8,142,800 $29,607,800
Allowances $1,124,000 $0 $1,124,000
Equipment $3,864,000 $360 $3,863,640
Total Project Financing $28,197,000 $8,142,440 $36,339,440