California Community Colleges Proposition 1D Project Details
Project Name Campus Center S&C Upgrades
CFIS 40.53.127
District SANTA BARBARA COMMUNITY COLLEGE DISTRICT
College SANTA BARBARA CITY COLLEGE
City Santa Barbara
County Santa Barbara
Senate District 19
Assembly District 37
Project Description and Status
Project Type Seismic
Date Funded 6/30/2014
Project Description The project provides construction funds for a new 23,655 assignable square feet (ASF) three-story building consisting of 1,904 ASF lecture space, 8,416 ASF laboratory space, 2,676 ASF office, 1,570 ASF library space, and 9,089 ASF other space.
Project Status In Preliminary Design
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 8/1/2014 7/30/2014
Preliminary Planning Approved, Design Begins 3/1/2015 3/16/2015
Design Approved, Authorized to go to Bid 8/15/2016
Construction Begins 11/15/2016
Facility Enters Into Use 11/15/2018
Project Closeout
Project Budget Summary
State Financing $20,432,000
Local/Non-State Financing $9,377,000
Total Financing $29,809,000
State Contact Eric Thorson
ethorson@cccco.edu
District Contact Julie Hendricks, AIA
8059650581
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $855,000 $403,000 $1,258,000
Working Drawings $772,000 $364,000 $1,136,000
Construction $18,805,000 $8,610,000 $27,415,000
Equipment $0 $0 $0
Total Project Financing $20,432,000 $9,377,000 $29,809,000
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $1,258,000 $0 $1,258,000
Working Drawings $1,136,000 $0 $1,136,000
Construction $27,415,000 $0 $27,415,000
Contract $25,907,000 $0 $25,907,000
Allowances $1,508,000 $0 $1,508,000
Equipment $0 $0 $0
Total Project Financing $29,809,000 $0 $29,809,000