California Community Colleges Proposition 1D Project Details
Project Name High Technology Center
CFIS 40.53.122
District SANTA BARBARA COMMUNITY COLLEGE DISTRICT
College SANTA BARBARA CITY COLLEGE
City Santa Barbara
County Santa Barbara
Senate District 19
Assembly District 35
Project Description and Status
Project Type Expand Instruction
Date Funded 7/31/2004
Project Description The project constructs a new high technology center to house the School of Media Arts (SoMA) including Multi-media Arts & Technology, Film Studies, Graphic Design & Photography, and Journalism. The SoMA project creates a 41,551 square foot facility with 5,385 square feet (sf) of lecture, 11,068 sf of laboratory, 4,198 sf of office, 3,720 sf of library, 11,060 sf of technology, and 6,120 sf of other space.
Project Status State Accounts Closed
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 8/1/2004 8/2/2004
Preliminary Planning Approved, Design Begins 8/1/2009 4/13/2007
Design Approved, Authorized to go to Bid 10/1/2010
Construction Begins 11/12/2010
Facility Enters Into Use 11/1/2012
Project Closeout 6/10/2013
Project Budget Summary
State Financing $1,400,000
Local/Non-State Financing $2,788,000
Total Financing $4,188,000
State Contact Eric Thorson
ethorson@cccco.edu
District Contact Julie Hendricks, AIA
8059650581
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $707,000 $1,410,000 $2,117,000
Working Drawings $693,000 $1,378,000 $2,071,000
Construction $0 $0 $0
Equipment $0 $0 $0
Total Project Financing $1,400,000 $2,788,000 $4,188,000
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $707,000 $1,410,000 $2,117,000
Working Drawings $693,000 $1,378,000 $2,071,000
Construction $18,221,000 $18,221,000 $0
Contract $17,319,000 $17,319,000 $0
Allowances $902,000 $902,000 $0
Equipment $2,098,000 $2,098,000 $0
Total Project Financing $21,719,000 $17,531,000 $4,188,000