Project Description and Status
Project Type Support Other
Date Funded 6/30/2006
Project Description The project constructs a 10,633 square foot maintenance complex that replaces an aged complex. The new facility will provide custodial, grounds and building maintenance services in a manner that complies with existing safety regulations and will contain 10,449 square feet (sf) of maintenance shops and storage and 184 sf of office.
Project Status State Accounts Closed
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 11/1/2006 11/14/2006
Preliminary Planning Approved, Design Begins 3/10/2007 3/9/2007
Design Approved, Authorized to go to Bid 9/17/2007 9/5/2007
Construction Begins 11/18/2007 11/21/2007
Facility Enters Into Use 11/18/2008 2/15/2010
Project Closeout 2/25/2011
Project Budget Summary
State Financing $4,889,000
Local/Non-State Financing $3,419,000
Total Financing $8,308,000
State Contact Lan Yuan
lyuan@cccco.edu
District Contact José Nuñez
6505746512
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $43,000 $187,000 $230,000
Working Drawings $49,000 $232,000 $281,000
Construction $4,547,000 $2,985,000 $7,532,000
Equipment $250,000 $15,000 $265,000
Total Project Financing $4,889,000 $3,419,000 $8,308,000
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $230,000 $0 $230,000
Working Drawings $281,000 $0 $281,000
Construction $6,329,000 $1,203,000 $7,532,000
Contract $5,939,000 $1,269,000 $7,208,000
Allowances $390,000 $66,000 $324,000
Equipment $250,000 $15,000 $265,000
Total Project Financing $7,090,000 $1,218,000 $8,308,000