California Community Colleges Proposition 1D Project Details
Project Name Electrical Infrastructure Replacement
CFIS 40.52.108
District SAN MATEO COUNTY COMMUNITY COLLEGE DISTRICT
College CANADA COLLEGE
City San Mateo
County San Mateo
Senate District 8
Assembly District 21
Project Description and Status
Project Type Infrastructure
Date Funded 2/20/2009
Project Description The project proposes to correct the safety and serviceability deficiencies of the aged electrical infrastructure at Cañada College including among other components the 12,000 volt fused service; switchgear and the 480 volt switchboards. The electrical system was constructed in the 1960s. The District commissioned Chevron Energy Solutions Company to assess the condition of the electrical infrastructure in 2006. The Company monitored performance of critical components and recorded actual performance under loand and found numerous instances of components that needed to be replaced or upgraded.
Project Status State Accounts Closed
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 10/15/2009 7/6/2009
Preliminary Planning Approved, Design Begins 7/1/2010 7/12/2010
Design Approved, Authorized to go to Bid 3/31/2011 3/15/2011
Construction Begins 6/1/2011 5/31/2011
Facility Enters Into Use 4/20/2012 4/20/2012
Project Closeout 5/15/2014
Project Budget Summary
State Financing $2,778,000
Local/Non-State Financing $1,174,853
Total Financing $3,952,853
State Contact Lan Yuan
lyuan@cccco.edu
District Contact José Nuñez
6505746512
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $185,000 $27,579 $212,579
Working Drawings $229,000 $0 $229,000
Construction $2,364,000 $1,147,274 $3,511,274
Equipment $0 $0 $0
Total Project Financing $2,778,000 $1,174,853 $3,952,853
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $185,000 $27,579 $212,579
Working Drawings $229,000 $0 $229,000
Construction $3,424,000 $97,274 $3,521,274
Contract $3,205,000 $28,517 $3,176,483
Allowances $219,000 $125,791 $344,791
Equipment $0 $0 $0
Total Project Financing $3,838,000 $124,853 $3,962,853