Project Name Reconstruction of Academic Facilities
CFIS 40.52.105
District SAN MATEO COUNTY COMMUNITY COLLEGE DISTRICT
College CANADA COLLEGE
City San Mateo
County San Mateo
Senate District 8
Assembly District 21
Project Description and Status
Project Type Expand Institution
Date Funded 8/24/2007
Project Description The project reconstructs 16,789 square feet of space vacated by the construction of the new library, learning resource and student services center and converts it into an assembly area, classrooms, offices and other space so that upper division courses previously available only at a four year postsecondary institutions can be made available on a community college campus. The project will create 3,503 square feet (sf) of lecture, 2,226 sf of office, 1,026 sf of library, 4,334 sf of assembly space and 5,700 sf of other instructional and institutional support space.
Project Status State Accounts Closed
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 7/1/2007 8/29/2007
Preliminary Planning Approved, Design Begins 5/15/2008 5/9/2008
Design Approved, Authorized to go to Bid 5/22/2009 6/30/2009
Construction Begins 1/1/2010 2/3/2010
Facility Enters Into Use 3/16/2012 3/16/2012
Project Closeout 8/6/2014
Project Budget Summary
State Financing $4,917,000
Local/Non-State Financing $8,713,775
Total Financing $13,630,775
State Contact Lan Yuan
lyuan@cccco.edu
District Contact José Nuñez
6505746512
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $57,000 $351,000 $408,000
Working Drawings $92,000 $402,000 $494,000
Construction $3,990,000 $7,399,126 $11,389,126
Equipment $778,000 $561,649 $1,339,649
Total Project Financing $4,917,000 $8,713,775 $13,630,775
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $408,000 $0 $408,000
Working Drawings $494,000 $0 $494,000
Construction $10,295,000 $1,094,126 $11,389,126
Contract $9,705,000 $383,126 $10,088,126
Allowances $590,000 $711,000 $1,301,000
Equipment $778,000 $561,649 $1,339,649
Total Project Financing $11,975,000 $1,655,775 $13,630,775