California Community Colleges Proposition 1D Project Details
Project Name Facility Maintenance Center
CFIS 40.52.104
District SAN MATEO COUNTY COMMUNITY COLLEGE DISTRICT
College CANADA COLLEGE
City San Mateo
County San Mateo
Senate District 8
Assembly District 21
Project Description and Status
Project Type Support Other
Date Funded 6/30/2006
Project Description The project constructs a facility maintenance center to replace space for maintenance activites created in the gymnasium. The project creates a 14,430 square foot facility with 790 square feet (sf) of offices and 13,640 sf of maintenance shops services and storage space.
Project Status State Accounts Closed
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 11/7/2006 11/14/2006
Preliminary Planning Approved, Design Begins 4/17/2007 5/24/2007
Design Approved, Authorized to go to Bid 11/21/2007 11/21/2007
Construction Begins 1/31/2008 1/18/2008
Facility Enters Into Use 2/28/2009 9/1/2009
Project Closeout 1/17/2012
Project Budget Summary
State Financing $6,933,000
Local/Non-State Financing $2,996,234
Total Financing $9,929,234
State Contact Lan Yuan
lyuan@cccco.edu
District Contact José Nuñez
6505746512
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $36,000 $251,000 $287,000
Working Drawings $84,000 $317,000 $401,000
Construction $6,509,000 $2,190,700 $8,699,700
Equipment $304,000 $237,534 $541,534
Total Project Financing $6,933,000 $2,996,234 $9,929,234
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $287,000 $0 $287,000
Working Drawings $388,000 $13,000 $401,000
Construction $7,388,000 $1,311,700 $8,699,700
Contract $6,954,000 $1,100,700 $8,054,700
Allowances $434,000 $211,000 $645,000
Equipment $304,000 $237,534 $541,534
Total Project Financing $8,367,000 $1,562,234 $9,929,234