California Community Colleges Proposition 1D Project Details
Project Name North County Learning Center/Library
CFIS 40.51.201
District SAN LUIS OBISPO DISTRICT
College NORTH COUNTY CENTER
City Paso Robles
County San Luis Obispo
Senate District 15
Assembly District 33
Project Description and Status
Project Type Expand Instruction
Date Funded 8/2/2003
Project Description The project constructs a 30,050 square foot Learning Resource Center. The project contains 5,100 square feet (sf) of lecture, 9,585 sf of laboratory, 5,750 sf of office, 6,000 sf of library, 1,565 asf technology, and 2,050 asf other support space.
Project Status Construction Complete
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 8/1/2003 8/6/2003
Preliminary Planning Approved, Design Begins 5/1/2004 2/6/2004
Design Approved, Authorized to go to Bid 11/1/2008 6/17/2005
Construction Begins 2/1/2010 2/2/2010
Facility Enters Into Use 5/1/2012 10/18/2012
Project Closeout
Project Budget Summary
State Financing $17,968,000
Local/Non-State Financing $0
Total Financing $17,968,000
State Contact Eric Thorson
ethorson@cccco.edu
District Contact Toni Sommer
8055463120
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $341,000 $0 $341,000
Working Drawings $361,000 $0 $361,000
Construction $15,695,000 $0 $15,695,000
Equipment $1,571,000 $0 $1,571,000
Total Project Financing $17,968,000 $0 $17,968,000
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $341,000 $0 $341,000
Working Drawings $361,000 $0 $361,000
Construction $9,542,000 $6,153,000 $15,695,000
Contract $8,963,000 $4,718,000 $13,681,000
Allowances $579,000 $1,435,000 $2,014,000
Equipment $1,439,000 $132,000 $1,571,000
Total Project Financing $11,683,000 $6,285,000 $17,968,000