Project Description and Status
Project Type Expand Instruction
Date Funded 8/24/2007
Project Description The project constructs a new 71,839 square foot Cunningham Math/Science Building. It will contain 40,427 square feet (sf) of laboratory, 11,796 sf of lecture, 12,118 sf of office, 4,498 sf of technology, and 3,000 sf of other space. The project will also demolish the 63,574 square foot math/science building built in 1973.
Project Status Under Construction
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 8/24/2007 8/29/2007
Preliminary Planning Approved, Design Begins 7/1/2008 6/17/2008
Design Approved, Authorized to go to Bid 6/15/2009 6/9/2009
Construction Begins 1/7/2010 1/19/2010
Facility Enters Into Use 3/31/2012
Project Closeout
Project Budget Summary
State Financing $22,278,000
Local/Non-State Financing $24,078,051
Total Financing $46,356,051
State Contact Jim Rogaski
jrogaski@cccco.edu
District Contact Stacy Pinola
2099545835
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $1,048,000 $1,048,219 $2,096,219
Working Drawings $1,254,000 $1,253,895 $2,507,895
Construction $19,172,000 $20,922,937 $40,094,937
Equipment $804,000 $853,000 $1,657,000
Total Project Financing $22,278,000 $24,078,051 $46,356,051
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $2,096,000 $438 $2,096,438
Working Drawings $2,508,000 $210 $2,507,790
Construction $55,406,000 $15,311,344 $40,094,656
Contract $52,879,000 $15,310,950 $37,568,050
Allowances $2,527,000 $394 $2,526,606
Equipment $1,657,000 $0 $1,657,000
Total Project Financing $61,667,000 $15,311,116 $46,355,884