California Community Colleges Proposition 1D Project Details
Project Name Campus Building
CFIS 40.48.301
District SAN FRANCISCO COMMUNITY COLLEGE DISTRICT
College SAN FRANCISCO CITY COLLEGE CHINATOWN CAMPUS
City San Francisco
County San Francisco
Senate District 8
Assembly District 12
Project Description and Status
Project Type Expand Instruction
Date Funded 8/24/2007
Project Description The project constructs a 91,104 square foot, multi-disciplinary campus facility in the Chinatown/North Beach neighborhood in the City of San Francisco. The building will contain 18,548 square feet (sf) of lecture, 28,638 sf of laboratory, 10,017 sf of office, 10,189 sf of library, 1,288 sf of technology and 22,424 sf of other space.
Project Status Construction Complete
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 7/1/2007 8/29/2007
Preliminary Planning Approved, Design Begins 6/1/2008 6/17/2008
Design Approved, Authorized to go to Bid 3/1/2009 9/2/2009
Construction Begins 4/1/2009 12/2/2009
Facility Enters Into Use 7/1/2011 1/3/2013
Project Closeout
Project Budget Summary
State Financing $46,755,000
Local/Non-State Financing $81,844,000
Total Financing $128,599,000
State Contact Harold Flood
hflood@cccco.edu
District Contact Ronald Gerhard
4152412229
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $167,000 $4,002,000 $4,169,000
Working Drawings $177,000 $4,519,000 $4,696,000
Construction $41,404,000 $73,323,000 $114,727,000
Equipment $5,007,000 $0 $5,007,000
Total Project Financing $46,755,000 $81,844,000 $128,599,000
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $4,169,000 $166 $4,168,834
Working Drawings $4,696,000 $386 $4,695,614
Construction $114,727,000 $61,472 $114,665,528
Contract $109,665,000 $150 $109,665,150
Allowances $5,062,000 $61,622 $5,000,378
Equipment $5,007,000 $343,420 $4,663,580
Total Project Financing $128,599,000 $405,444 $128,193,556