California Community Colleges Proposition 1D Project Details
Project Name Classroom/Lab Complex
CFIS 40.48.110
District SAN FRANCISCO COMMUNITY COLLEGE DISTRICT
College SAN FRANCISCO CITY COLLEGE OCEAN CAMPUS
City San Francisco
County San Francisco
Senate District 8
Assembly District 12
Project Description and Status
Project Type Expand Instruction
Date Funded 6/30/2006
Project Description This project develops the schematic designs for a 68,089 square foot classroom/laboratory complex for the theater, music, visual & media arts programs. Space types in the new facility include 5,225 square feet (sf) of lecture, 45,244 sf of laboratory, 4,200 sf of office and administrative support space, 5,450 sf of library and 1,970 sf of other space. The project will provide music labs, a recording studio and practice rooms for instruments and voice; a film sound stage and supporting labs for editing, graphics, digital effects, sound mixing and production. This project was terminated in November 2007 due to escalating costs. Program delivery could not be achieved within estimated budget.
Project Status State Accounts Closed
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 8/1/2006 11/16/2006
Preliminary Planning Approved, Design Begins 8/1/2007
Design Approved, Authorized to go to Bid 6/1/2008
Construction Begins 7/1/2008
Facility Enters Into Use 8/1/2010
Project Closeout 9/26/2007
Project Budget Summary
State Financing $0
Local/Non-State Financing $0
Total Financing $0
State Contact Harold Flood
hflood@cccco.edu
District Contact Peter Goldstein
4152412229
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $0 $0 $0
Working Drawings $0 $0 $0
Construction $0 $0 $0
Equipment $0 $0 $0
Total Project Financing $0 $0 $0
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $1,984,000 $1,984,000 $0
Working Drawings $2,641,000 $2,641,000 $0
Construction $56,229,000 $56,229,000 $0
Contract $53,695,000 $53,695,000 $0
Allowances $2,534,000 $2,534,000 $0
Equipment $2,254,000 $2,254,000 $0
Total Project Financing $63,108,000 $63,108,000 $0