California Community Colleges Proposition 1D Project Details
Project Name Learning Resource/Technology Center
CFIS 40.46.106
District SAN BERNARDINO COMMUNITY COLLEGE DISTRICT
College CRAFTON HILLS COLLEGE
City Yicapia
County San Bernardino
Senate District 31
Assembly District 63
Project Description and Status
Project Type Expand Instruction
Date Funded 6/30/2006
Project Description The project constructs a two-story, 40,000 square foot learning resource and technology center consisting of 2,160 square feet (sf) of laboratory space, 1,560 sf of office space, 17,935 sf of library space, 4,460 sf of technology space, and 13,885 sf of other space. The facility will contain specialized functions such as distance learning, media center, electronic commons, audiovisual learning, individual and group study, teleconferencing, and archives and special collections.
Project Status Construction Complete
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 9/1/2006 11/16/2006
Preliminary Planning Approved, Design Begins 6/1/2007 6/8/2007
Design Approved, Authorized to go to Bid 7/1/2008 5/19/2008
Construction Begins 9/1/2008 9/23/2008
Facility Enters Into Use 5/30/2011 5/30/2011
Project Closeout
Project Budget Summary
State Financing $15,545,000
Local/Non-State Financing $12,043,383
Total Financing $27,588,383
State Contact Lan Yuan
lyuan@cccco.edu
District Contact Tim Oliver
9093824021
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $559,000 $165,000 $724,000
Working Drawings $480,000 $343,000 $823,000
Construction $13,506,000 $11,058,383 $24,564,383
Equipment $1,000,000 $477,000 $1,477,000
Total Project Financing $15,545,000 $12,043,383 $27,588,383
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $724,000 $0 $724,000
Working Drawings $823,000 $0 $823,000
Construction $20,161,000 $4,403,383 $24,564,383
Contract $19,214,000 $4,191,978 $23,405,978
Allowances $947,000 $211,405 $1,158,405
Equipment $1,477,000 $0 $1,477,000
Total Project Financing $23,185,000 $4,403,383 $27,588,383