California Community Colleges Proposition 1D Project Details
Project Name Learning Resource Center Renovation
CFIS 40.45.217
District SOUTH ORANGE COUNTY COMMUNITY COLLEGE DISTRICT
College SADDLEBACK COLLEGE
City Mission Viejo
County Orange
Senate District 33
Assembly District 71
Project Description and Status
Project Type Modernize Instruction
Date Funded 6/30/2006
Project Description The project remodels the college's library building including converting space that was vacated when programs were relocated to the new Health Science/District Office building. Programs currently in portables will be relocated into the renovated building and the portables will be demolished. The resultant building will contain 74,537 total square feet (sf) with 8,218 sf of lecture, 10,489 sf of laboratory, 7,369 sf of offices, 41,102 sf of library, 4,608 sf of technology, and 2,751 sf of other space.
Project Status Construction Complete
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 8/1/2006 11/20/2006
Preliminary Planning Approved, Design Begins 9/1/2007 9/14/2007
Design Approved, Authorized to go to Bid 4/1/2010 6/4/2008
Construction Begins 6/1/2010 5/27/2010
Facility Enters Into Use 10/30/2012 10/30/2012
Project Closeout
Project Budget Summary
State Financing $15,673,000
Local/Non-State Financing $3,183,770
Total Financing $18,856,770
State Contact Lan Yuan
lyuan@cccco.edu
District Contact Brandye D'Lena
9495824678
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $530,000 $0 $530,000
Working Drawings $626,000 $129,526 $755,526
Construction $12,517,000 $2,837,007 $15,354,007
Equipment $2,000,000 $217,237 $2,217,237
Total Project Financing $15,673,000 $3,183,770 $18,856,770
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $589,000 $59,000 $530,000
Working Drawings $696,000 $59,526 $755,526
Construction $14,512,000 $842,007 $15,354,007
Contract $13,724,000 $577,581 $13,146,419
Allowances $788,000 $1,419,588 $2,207,588
Equipment $2,135,000 $82,237 $2,217,237
Total Project Financing $17,932,000 $924,770 $18,856,770