California Community Colleges Proposition 1D Project Details
Project Name Industrial Technology, Phase III
CFIS 40.44.308
District RIVERSIDE COMMUNITY COLLEGE DISTRICT
College NORCO CENTER
City Norco
County Riverside
Senate District 37
Assembly District 71
Project Description and Status
Project Type Expand Instruction
Date Funded 6/30/2006
Project Description The project constructs a 32,557 square foot high technology building for advanced integrated manufacturing/robotics and applied environmental technologies. Spaces in the facility include 8,550 square feet (sf) of lecture, 17,100 sf of laboratory, 2,490 sf of office and administrative support space and 4,417 sf of other space.
Project Status State Accounts Closed
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 8/1/2006 11/16/2006
Preliminary Planning Approved, Design Begins 2/1/2007 3/9/2007
Design Approved, Authorized to go to Bid 11/1/2007 10/11/2007
Construction Begins 12/1/2007 2/5/2008
Facility Enters Into Use 6/1/2009 10/19/2009
Project Closeout 2/27/2012
Project Budget Summary
State Financing $18,990,000
Local/Non-State Financing $9,675,826
Total Financing $28,665,826
State Contact Cheryl Larry
clarry@cccco.edu
District Contact Mr. Rick Hernandez
9512228471
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $188,000 $507,000 $695,000
Working Drawings $198,000 $944,000 $1,142,000
Construction $16,586,000 $5,804,500 $22,390,500
Equipment $2,018,000 $2,420,326 $4,438,326
Total Project Financing $18,990,000 $9,675,826 $28,665,826
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $695,000 $0 $695,000
Working Drawings $762,000 $380,000 $1,142,000
Construction $19,088,000 $3,255,500 $22,343,500
Contract $18,103,000 $3,100,000 $21,203,000
Allowances $985,000 $155,500 $1,140,500
Equipment $2,218,000 $2,220,600 $4,438,600
Total Project Financing $22,763,000 $5,856,100 $28,619,100