California Community Colleges Proposition 1D Project Details
Project Name WHEELOCK GYMNASIUM, SEISMIC RETROFIT
CFIS 40.44.105
District RIVERSIDE COMMUNITY COLLEGE DISTRICT
College RIVERSIDE CITY COLLEGE
City Riverside
County Riverside
Senate District 31
Assembly District 64
Project Description and Status
Project Type Seismic
Date Funded 9/23/2008
Project Description The project reconstructs the 28,751 square foot Wheelock Gymnasium to strengthen the structual design of the building. Space area affected by the project include 3,531 square feet (sf) of lecture, 258 sf of office and 24,962 sf of primarily physical education space.
Project Status Construction Complete
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 9/1/2008 9/25/2008
Preliminary Planning Approved, Design Begins 1/1/2009 10/12/2009
Design Approved, Authorized to go to Bid 4/1/2010 4/21/2010
Construction Begins 6/1/2010 6/7/2010
Facility Enters Into Use 1/1/2012 8/15/2012
Project Closeout
Project Budget Summary
State Financing $9,165,000
Local/Non-State Financing $7,450,000
Total Financing $16,615,000
State Contact Cheryl Larry
clarry@cccco.edu
District Contact Chris Carlson
9512228201
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $397,000 $274,000 $671,000
Working Drawings $421,000 $311,000 $732,000
Construction $8,347,000 $6,848,000 $15,195,000
Equipment $0 $17,000 $17,000
Total Project Financing $9,165,000 $7,450,000 $16,615,000
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $671,000 $0 $671,000
Working Drawings $732,000 $0 $732,000
Construction $16,991,000 $1,796,000 $15,195,000
Contract $16,139,000 $1,796,000 $14,343,000
Allowances $852,000 $0 $852,000
Equipment $17,000 $17,000 $0