California Community Colleges Proposition 1D Project Details
Project Name L Tower Seismic and Code Upgrades
CFIS 40.43.110
District RIO HONDO COMMUNITY COLLEGE DISTRICT
College RIO HONDO COLLEGE
City Whittier
County Los Angeles
Senate District 30
Assembly District 57
Project Description and Status
Project Type Seismic
Date Funded 6/30/2014
Project Description This proposal provides the seismic retrofit needed to address the structural deficiencies and the necessary renovations to comply with current accessibility and fire/life safety codes for the "L" Tower Building. The renovation to this 5-story, 31,120 asf/57,800 gsf building will consist of 7,549 af lecture, 12,035 lab, 6,360 asf office, 3,815 asf AV/TV, and 1,361 asf of Other space.
Project Status In Preliminary Design
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 12/1/2014 9/24/2014
Preliminary Planning Approved, Design Begins 6/1/2015 6/16/2015
Design Approved, Authorized to go to Bid 8/1/2016
Construction Begins 10/1/2016
Facility Enters Into Use 10/1/2017
Project Closeout
Project Budget Summary
State Financing $21,939,000
Local/Non-State Financing $252,000
Total Financing $22,191,000
State Contact Lan Yuan
lyuan@cccco.edu
District Contact James Poper
5629083441
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $959,000 $0 $959,000
Working Drawings $890,000 $252,000 $1,142,000
Construction $20,090,000 $0 $20,090,000
Equipment $0 $0 $0
Total Project Financing $21,939,000 $252,000 $22,191,000
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $959,000 $0 $959,000
Working Drawings $1,142,000 $0 $1,142,000
Construction $20,090,000 $0 $20,090,000
Contract $19,044,000 $0 $19,044,000
Allowances $1,046,000 $0 $1,046,000
Equipment $0 $0 $0
Total Project Financing $22,191,000 $0 $22,191,000