Project Description and Status
Project Type Support Instruction
Date Funded 6/30/2006
Project Description The project renovates a 22,130 square foot (sf) gymnasium and constructs of a 36,830 sf fitness center and locker rooms to replace a 25,251 sf facility built in 1966. The new building will contain 1,750 sf of PE laboratories, 3,085 sf of offices, 350 sf of technology support and 32,290 sf of physical education activity space.
Project Status Under Construction
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 11/1/2006 11/14/2006
Preliminary Planning Approved, Design Begins 5/1/2007 5/25/2007
Design Approved, Authorized to go to Bid 11/1/2009 5/1/2009
Construction Begins 6/1/2010 6/7/2010
Facility Enters Into Use 1/1/2014 10/30/2013
Project Closeout
Project Budget Summary
State Financing $16,382,000
Local/Non-State Financing $5,070,000
Total Financing $21,452,000
State Contact Lan Yuan
lyuan@cccco.edu
District Contact James Poper
5629083441
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $897,000 $267,000 $1,164,000
Working Drawings $787,000 $226,000 $1,013,000
Construction $14,425,000 $4,577,000 $19,002,000
Equipment $273,000 $0 $273,000
Total Project Financing $16,382,000 $5,070,000 $21,452,000
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $1,164,000 $0 $1,164,000
Working Drawings $1,013,000 $0 $1,013,000
Construction $25,484,000 $6,253,000 $19,231,000
Contract $24,162,000 $6,631,000 $17,531,000
Allowances $1,322,000 $378,000 $1,700,000
Equipment $273,000 $104 $273,104