California Community Colleges Proposition 1D Project Details
Project Name New Science/Humanities Building Seismic Replacement
CFIS 40.42.107
District REDWOODS COMMUNITY COLLEGE DISTRICT
College COLLEGE OF THE REDWOODS
City Eureka
County Humbolt
Senate District 2
Assembly District 2
Project Description and Status
Project Type Seismic
Date Funded 9/23/2008
Project Description The project constructs a new 38,030 square foot Science-Humanities building. Space types in the project include 17,195 square feet (sf) of lecture, 14,092 sf of laboratory, 1,793 sf of office, 636 sf of library reference and 4,344 sf of other space types. The building will replace three existing instructional buildings that sit directly on an active earthquake fault.
Project Status Construction Complete
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 10/1/2008 9/25/2008
Preliminary Planning Approved, Design Begins 6/1/2009 9/14/2009
Design Approved, Authorized to go to Bid 2/22/2011 2/22/2011
Construction Begins 4/22/2011 7/6/2011
Facility Enters Into Use 7/13/2013
Project Closeout
Project Budget Summary
State Financing $29,195,000
Local/Non-State Financing $1,652,000
Total Financing $30,847,000
State Contact Harold Flood
hflood@cccco.edu
District Contact Kathryn G. Smith
7074764170
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $1,148,000 $0 $1,148,000
Working Drawings $1,110,000 $0 $1,110,000
Construction $26,937,000 $0 $26,937,000
Equipment $0 $1,652,000 $1,652,000
Total Project Financing $29,195,000 $1,652,000 $30,847,000
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $1,148,000 $352 $1,147,648
Working Drawings $1,110,000 $115 $1,110,115
Construction $27,397,000 $499,880 $26,897,120
Contract $25,941,000 $456,000 $25,485,000
Allowances $1,456,000 $43,880 $1,412,120
Equipment $1,652,000 $125,770 $1,526,230
Total Project Financing $31,307,000 $625,887 $30,681,113