Project Name Student Services / Administration and Performing Arts Building
CFIS 40.42.106
District REDWOODS COMMUNITY COLLEGE DISTRICT
College COLLEGE OF THE REDWOODS
City Eureka
County Humbolt
Senate District 2
Assembly District 2
Project Description and Status
Project Type Seismic
Date Funded 8/24/2007
Project Description The project designs a new student services/administration building. Space types in the building include 5,547 square feet (sf) of laboratory space, 14,112 sf of office and administrative support space, 1,239 sf of library reference space and 2,510 sf of other space. The building will replace the existing student services/administration building and four 42-year old portable buildings that sit directly on several active earthquake faults.
Project Status Construction Complete
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 8/1/2007 8/29/2007
Preliminary Planning Approved, Design Begins 2/1/2008 2/8/2008
Design Approved, Authorized to go to Bid 3/29/2010 3/12/2010
Construction Begins 5/1/2010 5/17/2010
Facility Enters Into Use 12/30/2011 3/19/2013
Project Closeout
Project Budget Summary
State Financing $16,349,000
Local/Non-State Financing $1,791,280
Total Financing $18,140,280
State Contact Harold Flood
hflood@cccco.edu
District Contact Kathryn G. Smith
7074764170
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $710,000 $0 $710,000
Working Drawings $612,000 $0 $612,000
Construction $15,027,000 $649,280 $15,676,280
Equipment $0 $1,142,000 $1,142,000
Total Project Financing $16,349,000 $1,791,280 $18,140,280
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $710,000 $446 $709,554
Working Drawings $612,000 $384 $611,616
Construction $15,027,000 $649,280 $15,676,280
Contract $14,102,000 $648,500 $14,750,500
Allowances $925,000 $780 $925,780
Equipment $1,142,000 $474,385 $667,615
Total Project Financing $17,491,000 $174,065 $17,665,065