Project Name Technology and Engineering Complex
CFIS 40.36.204
District NORTH ORANGE COUNTY COMMUNITY COLLEGE DISTRICT
College FULLERTON COLLEGE
City Fullerton
County Orange
Senate District 33
Assembly District 72
Project Description and Status
Project Type Modernize Instruction
Date Funded 8/24/2007
Project Description The project designs the renovation of the Technical Education Building and the replacement of the Trade - Technical and the Automotive Technology buildings with a single facility. The project impacts 79,124 square feet on campus and will create 77,589 square feet (sf) including 14,870 sf of lecture space, 55,761 sf of laboratory space, 6,478 sf of office space and 480 sf of other space. The project will provide for technologically smart classrooms and laboratories designed to enable the presentation of current technology in numerous vocational programs.
Project Status Construction Complete
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 10/1/2007 8/28/2007
Preliminary Planning Approved, Design Begins 6/1/2008 6/17/2008
Design Approved, Authorized to go to Bid 1/15/2010 1/20/2010
Construction Begins 5/16/2011 3/1/2010
Facility Enters Into Use 3/1/2013 6/1/2012
Project Closeout
Project Budget Summary
State Financing $30,423,000
Local/Non-State Financing $3,380,533
Total Financing $33,803,533
State Contact Jim Rogaski
jrogaski@cccco.edu
District Contact Richard Williams
7148084893
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $1,093,000 $345,000 $1,438,000
Working Drawings $2,009,000 $0 $2,009,000
Construction $27,167,000 $3,018,533 $30,185,533
Equipment $154,000 $17,000 $171,000
Total Project Financing $30,423,000 $3,380,533 $33,803,533
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $1,438,000 $420 $1,438,420
Working Drawings $2,009,000 $352 $2,009,352
Construction $37,890,000 $7,704,818 $30,185,182
Contract $36,042,000 $7,690,538 $28,351,462
Allowances $1,848,000 $14,280 $1,833,720
Equipment $171,000 $0 $171,000
Total Project Financing $41,508,000 $7,704,046 $33,803,954