California Community Colleges Proposition 1D Project Details
Project Name General Classroom Building
CFIS 40.34.213
District MT. SAN JACINTO COMMUNITY COLLEGE DISTRICT
College MENIFEE VALLEY CENTER
City Menifiee
County Riverside
Senate District 37
Assembly District 65
Project Description and Status
Project Type Expand Instruction
Date Funded 6/30/2006
Project Description The project constructs a two-story, 22,200 square foot classroom building consisting of 7,600 square feet (sf) of lecture space, 8,400 sf of laboratory space, 2,000 sf of office and administrative support space, 1,000 sf of library space and 3,200 sf of other space. The project contains new technology to provide distance learning instructional programs.
Project Status State Accounts Closed
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 9/1/2006 11/16/2006
Preliminary Planning Approved, Design Begins 12/1/2006 10/16/2007
Design Approved, Authorized to go to Bid 2/1/2011 12/15/2010
Construction Begins 4/1/2011 5/16/2011
Facility Enters Into Use 5/1/2012 1/9/2013
Project Closeout 2/17/2016
Project Budget Summary
State Financing $14,067,000
Local/Non-State Financing $0
Total Financing $14,067,000
State Contact Harold Flood
hflood@cccco.edu
District Contact Becky Elam
9514873100
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $455,000 $0 $455,000
Working Drawings $470,000 $0 $470,000
Construction $11,899,000 $0 $11,899,000
Equipment $1,243,000 $0 $1,243,000
Total Project Financing $14,067,000 $0 $14,067,000
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $455,000 $0 $455,000
Working Drawings $470,000 $0 $470,000
Construction $11,759,000 $2,145,666 $9,613,334
Contract $11,130,000 $2,109,948 $9,020,052
Allowances $629,000 $35,718 $593,282
Equipment $1,235,000 $8,000 $1,243,000
Total Project Financing $13,919,000 $2,137,666 $11,781,334