California Community Colleges Proposition 1D Project Details
Project Name Davis Center Phase 2
CFIS 40.27.701
District LOS RIOS COMMUNITY COLLEGE DISTRICT
College DAVIS CENTER
City Davis
County Yolo
Senate District 3
Assembly District 4
Project Description and Status
Project Type Expand Instruction
Date Funded 6/30/2014
Project Description This project builds the second phase of permament buildings. It will provide 3,004 ASF of Lecture space, 7,282 ASF of Laboratory space, 2,520 ASF of Office space, 1,800 ASF of Library space, 200 ASF of AVTV space, and 1,000 ASF of Other space.
Project Status In Preliminary Design
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 8/1/2014
Preliminary Planning Approved, Design Begins 3/1/2015
Design Approved, Authorized to go to Bid 6/1/2016
Construction Begins 8/1/2016
Facility Enters Into Use 4/1/2018
Project Closeout
Project Budget Summary
State Financing $8,594,000
Local/Non-State Financing $5,758,000
Total Financing $14,352,000
State Contact Carlos Montoya
cmontoya@cccco.edu
District Contact Dave Clinchy
9168563409
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $117,000 $666,000 $783,000
Working Drawings $90,000 $361,000 $451,000
Construction $8,387,000 $4,037,000 $12,424,000
Equipment $0 $694,000 $694,000
Total Project Financing $8,594,000 $5,758,000 $14,352,000
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $783,000 $0 $783,000
Working Drawings $451,000 $0 $451,000
Construction $12,424,000 $0 $12,424,000
Contract $11,678,000 $0 $11,678,000
Allowances $746,000 $0 $746,000
Equipment $694,000 $0 $694,000
Total Project Financing $14,352,000 $0 $14,352,000