California Community Colleges Proposition 1D Project Details
Project Name Performing Arts Modernization
CFIS 40.27.313
District LOS RIOS COMMUNITY COLLEGE DISTRICT
College SACRAMENTO CITY COLLEGE
City Sacramento
County Sacramento
Senate District 5
Assembly District 4
Project Description and Status
Project Type Modernize Instruction
Date Funded 8/24/2007
Project Description The project remodels 34,034 square feet in the existing Performing Arts/Auditorium Building and converts it to 34,628 square feet with the following configuration to enhance its instructional function: 15,980 square feet (sf) for theater arts, 10,128 sf for instructional laboratories, 4,186 sf for offices, 3,914 sf for lecture and 420 sf for storage.
Project Status Construction Complete
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 8/1/2007 8/28/2007
Preliminary Planning Approved, Design Begins 9/1/2008 6/17/2008
Design Approved, Authorized to go to Bid 2/1/2010 3/22/2010
Construction Begins 6/1/2010 5/3/2010
Facility Enters Into Use 2/1/2012 1/1/2012
Project Closeout
Project Budget Summary
State Financing $14,035,000
Local/Non-State Financing $3,610,955
Total Financing $17,645,955
State Contact Carlos Montoya
cmontoya@cccco.edu
District Contact Dave Clinchy
9168563409
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $154,000 $406,730 $560,730
Working Drawings $127,000 $699,122 $826,122
Construction $13,754,000 $1,557,266 $15,311,266
Equipment $0 $947,837 $947,837
Total Project Financing $14,035,000 $3,610,955 $17,645,955
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $1,068,000 $507,270 $560,730
Working Drawings $820,000 $6,122 $826,122
Construction $17,534,000 $2,222,734 $15,311,266
Contract $16,580,000 $2,110,796 $14,469,204
Allowances $954,000 $111,938 $842,062
Equipment $976,000 $28,163 $947,837
Total Project Financing $20,398,000 $2,752,045 $17,645,955