California Community Colleges Proposition 1D Project Details
Project Name North East Buildings Modernization
CFIS 40.27.214
District LOS RIOS COMMUNITY COLLEGE DISTRICT
College COSUMNES RIVER COLLEGE
City Sacramento
County Sacramento
Senate District 6
Assembly District 9
Project Description and Status
Project Type Modernize Institution
Date Funded 2/20/2009
Project Description This project 1) demolishes and replaces four buildings for industrial technology and agriculture instructional programs, and 2) renovates an existing building for maintenance, custodial, and instituttional support spaces, resulting in 17,770 asf: 11,600 asf lab, 300 asf office and 13,750 asf other spaces.
Project Status Construction Complete
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 10/1/2009 8/9/2009
Preliminary Planning Approved, Design Begins 4/1/2010 4/21/2010
Design Approved, Authorized to go to Bid 3/1/2011 2/22/2011
Construction Begins 7/12/2011 5/16/2011
Facility Enters Into Use 12/1/2012 4/25/2013
Project Closeout
Project Budget Summary
State Financing $4,817,000
Local/Non-State Financing $4,101,273
Total Financing $8,918,273
State Contact Carlos Montoya
cmontoya@cccco.edu
District Contact Dave Clinchy
9168563409
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $97,000 $312,643 $409,643
Working Drawings $81,000 $416,276 $497,276
Construction $4,639,000 $2,803,354 $7,442,354
Equipment $0 $569,000 $569,000
Total Project Financing $4,817,000 $4,101,273 $8,918,273
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $658,000 $248,357 $409,643
Working Drawings $519,000 $21,724 $497,276
Construction $11,130,000 $3,687,646 $7,442,354
Contract $10,403,000 $3,564,499 $6,838,501
Allowances $727,000 $123,147 $603,853
Equipment $600,000 $31,000 $569,000
Total Project Financing $12,907,000 $3,988,727 $8,918,273