California Community Colleges Proposition 1D Project Details
Project Name Child Development Center
CFIS 40.26.804
District LOS ANGELES COMMUNITY COLLEGE DISTRICT
College LOS ANGELES VALLEY COLLEGE
City Los Angeles
County Los Angeles
Senate District 20
Assembly District 40
Project Description and Status
Project Type Support Instruction
Date Funded 6/30/2006
Project Description The project constructs a permanent Child Development Center for 105 children, replacing the existing CDC relocatables licensed for 62 children. When the new 18,551 square foot building is complete, the center will contain 3,100 sf of lecture, 841 sf of office 300 sf of library space and 14,310 sf of other space for the child development program and will be able to handle infants and toddlers up through school age.
Project Status Construction Complete
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 11/1/2006 11/17/2006
Preliminary Planning Approved, Design Begins 2/16/2007 6/8/2007
Design Approved, Authorized to go to Bid 4/17/2008 3/5/2008
Construction Begins 7/23/2008 6/3/2008
Facility Enters Into Use 10/2/2010 6/21/2010
Project Closeout
Project Budget Summary
State Financing $9,948,000
Local/Non-State Financing $5,407,578
Total Financing $15,355,578
State Contact Eric Thorson
ethorson@cccco.edu
District Contact Thomas Hall
2138912119
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $557,000 $87,159 $644,159
Working Drawings $343,000 $382,630 $725,630
Construction $8,606,000 $4,161,580 $12,767,580
Equipment $442,000 $776,209 $1,218,209
Total Project Financing $9,948,000 $5,407,578 $15,355,578
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $619,000 $25,159 $644,159
Working Drawings $381,000 $344,630 $725,630
Construction $9,562,000 $3,205,580 $12,767,580
Contract $9,022,000 $2,924,212 $11,946,212
Allowances $540,000 $281,368 $821,368
Equipment $491,000 $727,209 $1,218,209
Total Project Financing $11,053,000 $4,302,578 $15,355,578