California Community Colleges Proposition 1D Project Details
Project Name Physical Education Building Renovation
CFIS 40.26.510
District LOS ANGELES COMMUNITY COLLEGE DISTRICT
College LOS ANGELES PIERCE COLLEGE
City Los Angeles
County Los Angeles
Senate District 23
Assembly District 41
Project Description and Status
Project Type Support Instruction
Date Funded 6/30/2006
Project Description The project modernizes the Men's Gymnasium, the Women's Gymnasium, and the Swimming Pool Building. Total square feet (sf) reconstructed by the project is 64,446 sf including 98 sf of lecture, 9,456 sf of laboratory, 2,009 sf of office, 52,586 sf of physical education activity space and 297 sf other space.
Project Status Construction Complete
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 4/13/2007 11/17/2006
Preliminary Planning Approved, Design Begins 7/13/2007 7/13/2007
Design Approved, Authorized to go to Bid 4/30/2008 4/24/2008
Construction Begins 6/11/2008 6/12/2008
Facility Enters Into Use 10/31/2009 5/27/2010
Project Closeout
Project Budget Summary
State Financing $9,033,000
Local/Non-State Financing $9,033,000
Total Financing $18,066,000
State Contact Eric Thorson
ethorson@cccco.edu
District Contact Thomas Hall
2138912119
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $415,000 $415,000 $830,000
Working Drawings $369,000 $370,000 $739,000
Construction $7,926,000 $7,925,000 $15,851,000
Equipment $323,000 $323,000 $646,000
Total Project Financing $9,033,000 $9,033,000 $18,066,000
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $830,000 $0 $830,000
Working Drawings $739,000 $0 $739,000
Construction $15,851,000 $0 $15,851,000
Contract $15,006,000 $0 $15,006,000
Allowances $845,000 $0 $845,000
Equipment $646,000 $0 $646,000
Total Project Financing $18,066,000 $0 $18,066,000