California Community Colleges Proposition 1D Project Details
Project Name Media Arts Center
CFIS 40.26.411
District LOS ANGELES COMMUNITY COLLEGE DISTRICT
College LOS ANGELES MISSION COLLEGE
City Los Angeles
County Los Angeles
Senate District 28
Assembly District 55
Project Description and Status
Project Type Support Instruction
Date Funded 8/24/2007
Project Description The project builds permanent facilities for the Media Arts program and moves out of leased off-campus space. The new 26,192 square foot facilities will include 966 square feet (sf) of lecture, 9,472 sf of laboratory, 1,906 sf of office, 676 sf of library, 276 sf of technology, and 12,896 sf of other support space.
Project Status Under Construction
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 7/1/2007 8/29/2007
Preliminary Planning Approved, Design Begins 5/7/2008 8/8/2008
Design Approved, Authorized to go to Bid 3/1/2009 6/16/2009
Construction Begins 8/21/2009 9/2/2009
Facility Enters Into Use 3/31/2017
Project Closeout
Project Budget Summary
State Financing $11,795,000
Local/Non-State Financing $13,985,063
Total Financing $25,780,063
State Contact Eric Thorson
ethorson@cccco.edu
District Contact Thomas Hall
2138912119
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $520,000 $521,000 $1,041,000
Working Drawings $554,000 $1,278,063 $1,832,063
Construction $10,338,000 $11,803,000 $22,141,000
Equipment $383,000 $383,000 $766,000
Total Project Financing $11,795,000 $13,985,063 $25,780,063
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $1,041,000 $0 $1,041,000
Working Drawings $1,107,000 $725,063 $1,832,063
Construction $25,156,000 $3,014,000 $22,142,000
Contract $24,019,000 $3,014,000 $21,005,000
Allowances $1,137,000 $0 $1,137,000
Equipment $766,000 $0 $766,000
Total Project Financing $28,070,000 $2,288,937 $25,781,063