California Community Colleges Proposition 1D Project Details
Project Name Library/Learning Resource Center
CFIS 40.26.305
District LOS ANGELES COMMUNITY COLLEGE DISTRICT
College LOS ANGELES HARBOR COLLEGE
City Los Angeles
County Los Angeles
Senate District 28
Assembly District 55
Project Description and Status
Project Type Modernize Instruction
Date Funded 8/24/2007
Project Description The project demolishes the obsolete 56-year-old library building and builds a new 30,106 square foot library/learning resource center. The new space will include 2,310 square feet (sf) of laboratory, 1,440 sf of office, 20,751 sf of library, 1,785 sf of technology, and 3,820 sf of library support space.
Project Status Construction Complete
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 7/1/2007 8/29/2007
Preliminary Planning Approved, Design Begins 1/1/2008 6/17/2008
Design Approved, Authorized to go to Bid 6/1/2009 6/24/2009
Construction Begins 4/1/2010 3/22/2010
Facility Enters Into Use 3/31/2014 2/14/2014
Project Closeout
Project Budget Summary
State Financing $9,867,000
Local/Non-State Financing $9,867,000
Total Financing $19,734,000
State Contact Eric Thorson
ethorson@cccco.edu
District Contact Thomas Hall
2138912119
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $704,000 $704,000 $1,408,000
Working Drawings $514,000 $514,000 $1,028,000
Construction $8,347,000 $8,348,000 $16,695,000
Equipment $302,000 $301,000 $603,000
Total Project Financing $9,867,000 $9,867,000 $19,734,000
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $1,408,000 $0 $1,408,000
Working Drawings $1,027,000 $1,000 $1,028,000
Construction $25,532,000 $8,837,000 $16,695,000
Contract $24,345,000 $8,837,000 $15,508,000
Allowances $1,187,000 $0 $1,187,000
Equipment $603,000 $0 $603,000
Total Project Financing $28,570,000 $8,836,000 $19,734,000