California Community Colleges Proposition 1D Project Details
Project Name Jefferson Hall Modernization
CFIS 40.26.209
District LOS ANGELES COMMUNITY COLLEGE DISTRICT
College LOS ANGELES CITY COLLEGE
City Los Angeles
County Los Angeles
Senate District 22
Assembly District 45
Project Description and Status
Project Type Modernize Instruction
Date Funded 8/24/2007
Project Description The project renovates the 47-year-old Jefferson Hall Building to provide an efficient configuration of classrooms, computer labs, and support spaces. The remodeled building will have 21,124 square feet (sf) of lecture, 3,060 sf of laboratories, 6,719 sf of offices, and 557 sf of technology space.
Project Status Construction Complete
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 7/1/2007 8/29/2007
Preliminary Planning Approved, Design Begins 4/16/2008 6/17/2008
Design Approved, Authorized to go to Bid 8/1/2009 6/16/2009
Construction Begins 2/1/2010 2/25/2010
Facility Enters Into Use 8/25/2011 9/9/2011
Project Closeout
Project Budget Summary
State Financing $4,024,000
Local/Non-State Financing $3,968,000
Total Financing $7,992,000
State Contact Eric Thorson
ethorson@cccco.edu
District Contact Thomas Hall
2138912119
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $173,000 $173,000 $346,000
Working Drawings $171,000 $171,000 $342,000
Construction $3,487,000 $3,432,000 $6,919,000
Equipment $193,000 $192,000 $385,000
Total Project Financing $4,024,000 $3,968,000 $7,992,000
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $346,000 $0 $346,000
Working Drawings $342,000 $0 $342,000
Construction $6,974,000 $55,000 $6,919,000
Contract $6,527,000 $205,130 $6,321,870
Allowances $447,000 $150,130 $597,130
Equipment $385,000 $0 $385,000
Total Project Financing $8,047,000 $55,000 $7,992,000