California Community Colleges Proposition 1D Project Details
Project Name Multi-Media Classrooms
CFIS 40.26.108
District LOS ANGELES COMMUNITY COLLEGE DISTRICT
College EAST LOS ANGELES COLLEGE
City Los Angeles
County Los Angeles
Senate District 24
Assembly District 49
Project Description and Status
Project Type Modernize Instruction
Date Funded 6/30/2006
Project Description The project removes two functionally inadequate classroom buildings and constructs a new multi-media instructional building. The new space will total 28,886 square feet (sf) and includes 16,540 sf of classroom; 6,381 sf of laboratories; 5,228 sf of offices and 737 sf of other space.
Project Status Construction Complete
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 1/31/2007 11/17/2006
Preliminary Planning Approved, Design Begins 5/15/2007 6/8/2007
Design Approved, Authorized to go to Bid 11/15/2008 5/27/2008
Construction Begins 10/15/2009 3/4/2009
Facility Enters Into Use 8/30/2011 8/30/2011
Project Closeout
Project Budget Summary
State Financing $15,063,000
Local/Non-State Financing $297,000
Total Financing $15,360,000
State Contact Eric Thorson
ethorson@cccco.edu
District Contact Thomas Hall
2138912119
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $730,000 $0 $730,000
Working Drawings $600,000 $0 $600,000
Construction $13,280,000 $0 $13,280,000
Equipment $453,000 $297,000 $750,000
Total Project Financing $15,063,000 $297,000 $15,360,000
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $730,000 $45 $729,955
Working Drawings $600,000 $282 $599,718
Construction $15,221,000 $1,941,000 $13,280,000
Contract $14,502,000 $1,941,000 $12,561,000
Allowances $719,000 $0 $719,000
Equipment $453,000 $297,000 $750,000
Total Project Financing $17,004,000 $1,644,327 $15,359,673