California Community Colleges Proposition 1D Project Details
Project Name Wellness Center
CFIS 40.22.307
District KERN COMMUNITY COLLEGE DISTRICT
College PORTERVILLE COLLEGE
City Porterville
County Tulare
Senate District 18
Assembly District 34
Project Description and Status
Project Type Support Instruction
Date Funded 6/30/2006
Project Description The project renovates and expands an existing physical education facility. The project scope involves a total of 10,546 square feet (sf), with 6,055 sf of new space and 4,491 sf of remodeled space. The project creates 9,915 sf of physical education activity space, 240 sf of office, and 390 sf of storage space.
Project Status State Accounts Closed
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 7/1/2006 11/20/2006
Preliminary Planning Approved, Design Begins 10/1/2006 6/8/2007
Design Approved, Authorized to go to Bid 7/1/2007 5/5/2008
Construction Begins 9/1/2007 6/23/2008
Facility Enters Into Use 10/1/2008 9/15/2009
Project Closeout 9/1/2009
Project Budget Summary
State Financing $3,498,000
Local/Non-State Financing $3,948,000
Total Financing $7,446,000
State Contact Hoang Nguyen
hnguyen@cccco.edu
District Contact Thomas Burke
6613365117
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $123,000 $123,000 $246,000
Working Drawings $172,000 $171,000 $343,000
Construction $2,926,000 $3,378,000 $6,304,000
Equipment $277,000 $276,000 $553,000
Total Project Financing $3,498,000 $3,948,000 $7,446,000
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $246,000 $0 $246,000
Working Drawings $343,000 $0 $343,000
Construction $5,854,000 $450,000 $6,304,000
Contract $5,470,000 $450,000 $5,920,000
Allowances $384,000 $0 $384,000
Equipment $553,000 $0 $553,000
Total Project Financing $6,996,000 $450,000 $7,446,000