Project Description and Status
Project Type Modernize Instruction
Date Funded 6/30/2006
Project Description The project remodels 12,419 square feet (sf) of the third floor of Main Building for science labs, laboratory support spaces, student services space, and offices. The project will create 4,552 sf of laboratory, 4,498 sf of office, 1,300 sf of meeting areas, and 1,970 sf of other space.
Project Status State Accounts Closed
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 7/1/2006 11/20/2006
Preliminary Planning Approved, Design Begins 9/1/2006 6/8/2007
Design Approved, Authorized to go to Bid 6/1/2008 6/2/2008
Construction Begins 7/11/2008 6/20/2008
Facility Enters Into Use 10/1/2010 10/10/2010
Project Closeout 11/6/2012
Project Budget Summary
State Financing $2,780,000
Local/Non-State Financing $4,784,755
Total Financing $7,564,755
State Contact Hoang Nguyen
hnguyen@cccco.edu
District Contact Thomas Burke
6613365117
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $100,000 $100,000 $200,000
Working Drawings $145,000 $145,000 $290,000
Construction $2,535,000 $4,539,755 $7,074,755
Equipment $0 $0 $0
Total Project Financing $2,780,000 $4,784,755 $7,564,755
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $200,000 $0 $200,000
Working Drawings $290,000 $0 $290,000
Construction $5,070,000 $2,004,755 $7,074,755
Contract $4,748,000 $2,004,755 $6,752,755
Allowances $322,000 $0 $322,000
Equipment $0 $0 $0