California Community Colleges Proposition 1D Project Details
Project Name BLDG 400 MODERNIZATION
CFIS 40.21.105
District IMPERIAL DISTRICT
College IMPERIAL VALLEY COLLEGE
City Imperial
County Imperial
Senate District 40
Assembly District 80
Project Description and Status
Project Type Modernize Instruction
Date Funded 2/20/2009
Project Description This project renovates 8,321 asf in Building 400, a 44 year-old building, and removes three buildings that are in poor condition and/or temporary and do not comply with current building standards. Modernized space includes 4,417 asf lecture, 2,422 asf clinic/counseling services, 889 ask AV/TV, 463 asf office, and 130 asf other space
Project Status Construction Complete
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 9/1/2009 7/22/2009
Preliminary Planning Approved, Design Begins 3/15/2010 3/15/2010
Design Approved, Authorized to go to Bid 4/28/2011 3/16/2011
Construction Begins 5/18/2011 6/8/2011
Facility Enters Into Use 8/1/2012 1/9/2013
Project Closeout
Project Budget Summary
State Financing $2,258,000
Local/Non-State Financing $4,104,104
Total Financing $6,362,104
State Contact Cheryl Larry
clarry@cccco.edu
District Contact John Lau
7603556235
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $98,000 $183,356 $281,356
Working Drawings $111,000 $149,761 $260,761
Construction $2,049,000 $3,456,072 $5,505,072
Equipment $0 $314,915 $314,915
Total Project Financing $2,258,000 $4,104,104 $6,362,104
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $196,000 $85,356 $281,356
Working Drawings $221,000 $39,761 $260,761
Construction $4,185,000 $1,320,072 $5,505,072
Contract $4,108,000 $1,114,072 $5,222,072
Allowances $77,000 $206,000 $283,000
Equipment $0 $314,915 $314,915
Total Project Financing $4,602,000 $1,760,104 $6,362,104