California Community Colleges Proposition 1D Project Details
Project Name Center for Applied Technology
CFIS 40.20.103
District HARTNELL JOINT COMMUNITY COLLEGE DISTRICT
College HARTNELL COLLEGE
City Salinas
County Monterey
Senate District 12
Assembly District 28
Project Description and Status
Project Type Expand Instruction
Date Funded 6/30/2006
Project Description The project constructs a 40,000 square foot applied technology building and creates 24,050 square feet (sf) of laboratory, 7,200 sf of lecture, 3,080 sf of office, 1,500 sf of library, 1,460 sf of technology and 2,720 sf of other space.
Project Status State Accounts Closed
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 8/1/2006 11/20/2006
Preliminary Planning Approved, Design Begins 1/1/2007 10/16/2007
Design Approved, Authorized to go to Bid 1/1/2008 4/4/2008
Construction Begins 2/15/2008 6/23/2008
Facility Enters Into Use 11/1/2010 1/11/2011
Project Closeout 12/1/2013
Project Budget Summary
State Financing $13,172,000
Local/Non-State Financing $13,337,000
Total Financing $26,509,000
State Contact Hoang Nguyen
hnguyen@cccco.edu
District Contact Damon Felice
8317707044
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $373,000 $373,000 $746,000
Working Drawings $507,000 $508,000 $1,015,000
Construction $10,746,000 $10,746,000 $21,492,000
Equipment $1,546,000 $1,710,000 $3,256,000
Total Project Financing $13,172,000 $13,337,000 $26,509,000
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $746,000 $0 $746,000
Working Drawings $1,015,000 $0 $1,015,000
Construction $22,804,000 $1,312,000 $21,492,000
Contract $21,685,000 $1,312,000 $20,373,000
Allowances $1,119,000 $0 $1,119,000
Equipment $3,130,000 $126,000 $3,256,000
Total Project Financing $27,695,000 $1,186,000 $26,509,000