California Community Colleges Proposition 1D Project Details
Project Name HEALTH SCIENCES BUILDING
CFIS 40.19.210
District GROSSMONT-CUYAMACA COMMUNITY COLLEGE DISTRICT
College GROSSMONT COLLEGE
City El Cajon
County San Diego
Senate District 36
Assembly District 77
Project Description and Status
Project Type Expand Instruction
Date Funded 6/30/2006
Project Description The project constructs a new 39,328 square foot health science building and creates 7,180 square feet (sf) of lecture, 25,868 sf of laboratory, 5,930 sf of office, and 350 sf of other space. The project also demolishes a building of 17,052 sf that has structural deficiencies.
Project Status State Accounts Closed
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 3/1/2006 11/17/2006
Preliminary Planning Approved, Design Begins 8/1/2006 9/14/2007
Design Approved, Authorized to go to Bid 6/1/2007 5/28/2008
Construction Begins 7/15/2007 6/25/2008
Facility Enters Into Use 1/15/2009 10/15/2010
Project Closeout 4/14/2015
Project Budget Summary
State Financing $14,043,000
Local/Non-State Financing $15,635,065
Total Financing $29,678,065
State Contact Harold Flood
hflood@cccco.edu
District Contact Sue Rearic
6196447575
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $103,000 $1,118,733 $1,221,733
Working Drawings $117,000 $1,085,093 $1,202,093
Construction $12,806,000 $13,202,425 $26,008,425
Equipment $1,017,000 $228,814 $1,245,814
Total Project Financing $14,043,000 $15,635,065 $29,678,065
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $950,000 $271,733 $1,221,733
Working Drawings $984,000 $218,093 $1,202,093
Construction $24,582,000 $1,426,425 $26,008,425
Contract $23,411,000 $1,382,886 $22,028,114
Allowances $1,171,000 $2,809,311 $3,980,311
Equipment $1,637,000 $391,431 $1,245,569
Total Project Financing $28,153,000 $1,524,820 $29,677,820