California Community Colleges Proposition 1D Project Details
Project Name BUSINESS/CIS BUILDING
CFIS 40.19.118
District GROSSMONT-CUYAMACA COMMUNITY COLLEGE DISTRICT
College CUYAMACA COLLEGE
City El Cajon
County San Diego
Senate District 36
Assembly District 77
Project Description and Status
Project Type Expand Instruction
Date Funded 6/30/2006
Project Description The project constructs a new 33,245 square foot (sf) two-story laboratory building for the business and computer information instructional programs. The project includes 910 sf of lecture, 26,610 sf of laboratory, 4,070 sf of office, 770 sf of technology , and 885 sf of other space. The project will remove an existing wood frame, one story building to accommodate the site footprint required for the new building.
Project Status State Accounts Closed
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 11/1/2006 11/17/2006
Preliminary Planning Approved, Design Begins 9/1/2007 9/14/2007
Design Approved, Authorized to go to Bid 5/1/2008 5/27/2008
Construction Begins 6/1/2008 6/30/2008
Facility Enters Into Use 6/1/2010 10/15/2010
Project Closeout 2/16/2016
Project Budget Summary
State Financing $12,903,000
Local/Non-State Financing $9,927,329
Total Financing $22,830,329
State Contact Harold Flood
hflood@cccco.edu
District Contact Sue Rearic
6196447575
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $172,000 $722,985 $894,985
Working Drawings $140,000 $618,000 $758,000
Construction $10,133,000 $8,586,344 $18,719,344
Equipment $2,458,000 $0 $2,458,000
Total Project Financing $12,903,000 $9,927,329 $22,830,329
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $895,000 $15 $894,985
Working Drawings $758,000 $0 $758,000
Construction $18,968,000 $248,656 $18,719,344
Contract $18,033,000 $248,656 $17,784,344
Allowances $935,000 $0 $935,000
Equipment $4,522,000 $2,064,000 $2,458,000
Total Project Financing $25,143,000 $2,312,671 $22,830,329