California Community Colleges Proposition 1D Project Details
Project Name REPLACE WATER SUPPLY SYSTEM
CFIS 40.17.111
District GAVILAN DISTRICT
College GAVILAN COLLEGE
City Gilroy
County San Benito
Senate District 15
Assembly District 28
Project Description and Status
Project Type Infrastructure
Date Funded 10/8/2010
Project Description This project replaces the 1,000,000 gallon steel water tank with 2 smaller tanks and upgrades the water supply system to current code requirements.
Project Status Out to Bid
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 12/1/2010 10/26/2010
Preliminary Planning Approved, Design Begins 1/15/2013 1/1/2013
Design Approved, Authorized to go to Bid 10/5/2013 5/21/2013
Construction Begins 2/1/2014
Facility Enters Into Use 6/30/2015
Project Closeout
Project Budget Summary
State Financing $6,590,000
Local/Non-State Financing $0
Total Financing $6,590,000
State Contact Jim Rogaski
jrogaski@cccco.edu
District Contact Steven Kinsella
4088484712
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $332,000 $0 $332,000
Working Drawings $289,000 $0 $289,000
Construction $5,969,000 $0 $5,969,000
Equipment $0 $0 $0
Total Project Financing $6,590,000 $0 $6,590,000
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $332,000 $464 $332,464
Working Drawings $289,000 $481 $288,519
Construction $5,969,000 $350,512 $5,618,488
Contract $5,594,000 $350,600 $5,243,400
Allowances $375,000 $88 $375,088
Equipment $0 $0 $0
Total Project Financing $6,590,000 $350,529 $6,239,471