California Community Colleges Proposition 1D Project Details
Project Name Instructional Building 1 Replacement
CFIS 40.14.204
District EL CAMINO COMMUNITY COLLEGE DISTRICT
College EL CAMINO COLLEGE COMPTON CENTER
City Compton
County Los Angeles
Senate District 35
Assembly District 64
Project Description and Status
Project Type Seismic
Date Funded 6/30/2014
Project Description This project plans to replace old, seismically unsafe buildings at El Camino College Compton Center (Compton Center) with a new instructional building. The new building will be a 2-story building with 17,180 assignable square feet (ASF), including 9,575 ASF lecture, 4,175 ASF laboratory, 3,180 ASF office, and 250 ASF other space
Project Status In Preliminary Design
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 8/1/2014
Preliminary Planning Approved, Design Begins 2/3/2016
Design Approved, Authorized to go to Bid 2/16/2017
Construction Begins 5/19/2017
Facility Enters Into Use 6/3/2019
Project Closeout
Project Budget Summary
State Financing $14,220,000
Local/Non-State Financing $3,572,000
Total Financing $17,792,000
State Contact Hoang Nguyen
hnguyen@cccco.edu
District Contact Dr. Keith Curry
3109001600
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $223,000 $399,000 $622,000
Working Drawings $559,000 $427,000 $986,000
Construction $13,438,000 $2,746,000 $16,184,000
Equipment $0 $0 $0
Total Project Financing $14,220,000 $3,572,000 $17,792,000
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $622,000 $0 $622,000
Working Drawings $986,000 $0 $986,000
Construction $16,184,000 $0 $16,184,000
Contract $15,095,000 $0 $15,095,000
Allowances $1,089,000 $0 $1,089,000
Equipment $0 $0 $0
Total Project Financing $17,792,000 $0 $17,792,000