Project Description and Status
Project Type Infrastructure
Date Funded 2/20/2009
Project Description The project finances the repair and replacement of the campus water, sewer, and other infrastructure systems that are failing on the campus.
Project Status Under Construction
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 9/1/2009 8/14/2009
Preliminary Planning Approved, Design Begins 6/14/2010 6/14/2010
Design Approved, Authorized to go to Bid 6/22/2011 6/22/2011
Construction Begins 9/1/2012 8/2/2012
Facility Enters Into Use 12/1/2013
Project Closeout
Project Budget Summary
State Financing $12,682,000
Local/Non-State Financing $1,166,000
Total Financing $13,848,000
State Contact Hoang Nguyen
hnguyen@cccco.edu
District Contact Dr. Keith Curry
3109001600
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $215,000 $573,000 $788,000
Working Drawings $825,000 $0 $825,000
Construction $11,642,000 $593,000 $12,235,000
Equipment $0 $0 $0
Total Project Financing $12,682,000 $1,166,000 $13,848,000
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $788,000 $0 $788,000
Working Drawings $825,000 $0 $825,000
Construction $17,083,000 $4,848,000 $12,235,000
Contract $16,078,000 $4,848,000 $11,230,000
Allowances $1,005,000 $0 $1,005,000
Equipment $0 $0 $0
Total Project Financing $18,696,000 $4,848,000 $13,848,000